How do contingency fees affect the initial cost estimates of PSH projects

How do contingency fees affect the initial cost estimates of PSH projects

Contingency fees significantly impact the initial cost estimates of Pumped Storage Hydropower (PSH) projects by adding a substantial markup to the direct and total project costs. Specifically:

  • Contingency fees are typically applied as a percentage of the direct costs or the total installed cost of the project. For PSH projects, a commonly used contingency fee is around 33% of direct costs, which corresponds to about 25% of the total project cost.
  • These contingency fees cover uncertainties and potential cost overruns in construction and engineering, reflecting risks associated with excavation, tunnels, structures, and electromechanical equipment, which collectively form a large portion of the project budget.
  • In detailed cost breakdowns, contingency fees are added on top of direct costs (materials, labor, equipment) and indirect costs (engineering, project management), thereby increasing the initial cost estimate by a significant margin to accommodate unforeseen expenses and ensure financial feasibility.
  • For example, if the direct costs of a PSH project are estimated at $100 million, a 33% contingency fee would add an additional $33 million, increasing the initial cost estimate to $133 million before other indirect costs are factored in.

Thus, contingency fees act as a critical buffer in the budget planning of PSH projects, increasing initial cost estimates to provide a more realistic and risk-adjusted financial outlook for project developers and stakeholders.

Original article by NenPower, If reposted, please credit the source: https://nenpower.com/blog/how-do-contingency-fees-affect-the-initial-cost-estimates-of-psh-projects/

Like (0)
NenPowerNenPower
Previous February 4, 2025 11:47 pm
Next February 5, 2025 12:27 am

相关推荐